HWS Cylinder Replacement for AIG

FenchurchStreetMain

Project is to replace 2 old, out of date, damaged hot water cylinders and replace with new including a new water softener to help reduce the effects of lime scale.

We are currently in week 2 of a 3 week project. We have replaced one cylinder. The new cylinder has been pressure tested and is ready to go live.

The same process will be carried out this weekend for the remaining cylinder and this will be pressure tested on Tuesday and again made live the following weekend. 